The challenge
The operator had drilled the acreage before with inconsistent results: spud-to-spud times varied by more than 40% across a six-well programme, with most of the variance appearing in the curve and in rig-move time between wellheads.
Our approach
We reviewed every offset well on the acreage before mobilising, standardised the BHA and bit programme across all eight wells, and moved to a walking substructure that repositioned between wellheads without rigging down. Daily performance was measured against the plan and reviewed with the operator each morning.
The outcome
Spud-to-spud time reduced progressively across the pad, with the final wells drilled materially faster than the programme average and no recordable incidents across the campaign.
More case studies

Turnaround Maintenance
Refinery unit turnaround
A planned unit shutdown where the scope was challenged before the schedule was built, rather than after it slipped.
Read more
Well Servicing
Field-wide workover and production recovery
A mature field where repeat rod failures were being treated as a maintenance cost rather than as a solvable engineering problem.
Read more